Do your audits find risk, or just fill the calendar?
Audit Management plans system, process and product audits by risk, computes the VDA 6.3 class, runs Layered Process Audits on a phone and follows every nonconformity to verified effectiveness.
Risk sets each audit interval
VDA 6.3 class computed, not typed
LPAs on a phone, even offline
AUD-000042 · VDA 6.3 process auditFollow-up open
Machining line 2 — pump housingClosing meeting 12 Mar 2026 · Report R1 issued
EG(P5P6P7)90 %A by scoreClass B
P5Supplier management94 %
P6Production process analysis88 %
P7Customer care96 %
DG-B3 · Star question P6.2.3 scored 4 — capped at B
Findings3 recorded
F01
Major NCP6.2.3Reaction plan for bore diameter not applied at OP 30Open — response due· due 27 MarCAPA-000231 · D4
F02
Minor NCP6.4.2Spindle maintenance overdue on two machinesResponse submitted· due 11 May
F03
ObservationP6.4.4Gauge rack could sit closer to the stationClosed
The method
What is audit management under IATF 16949?
Audit management is planning, running and following up internal and supplier audits so that they find risk instead of filling a calendar. IATF 16949 clause 9.2.2 asks for a risk-based internal audit programme that covers the quality management system and every manufacturing process on every shift, including the shift handover, within a three-year cycle, and that audits products at defined stages. ISO 19011 gives the guidance for managing the programme and conducting each audit.
Zometric starts from an audit universe: QMS processes, manufacturing processes, products, suppliers, software development and remote support functions. Each item gets a risk score from its open findings, its last audit result, customer complaints, High Action Priority chains in the PFMEA and recent changes. The score proposes an interval, a person confirms it with a written reason, and the audit client approves the year's programme.
Each audit then follows one lifecycle from preparation to closure. VDA 6.3 process audits and P1 potential analyses are scored by the product, and Layered Process Audits run on their own schedule of layers and areas, following the practice described in AIAG CQI-8.
Why teams switch
Problems Zometric Audit Management removes
Six problems audit programme managers describe in their own words — and what changes when the programme, the audits and the layered audits share one record.
01Programme
Our audit plan is last year's plan with new dates.
With Zometric
Every universe item carries a risk score from open findings, the last audit, complaints, PFMEA risk and changes. The score proposes an interval, and a new complaint, nonconformity or process change opens a frequency review.
Risk-based audit universe
02Shift coverage
The certification auditor asked which shifts we audited, and we could not say.
With Zometric
Each manufacturing process shows every shift and the shift handover as covered, planned or missing in the three-year cycle. The proposed plan picks up the missing shifts and the handover.
Shift and handover coverage
03VDA 6.3
Our VDA 6.3 workbook said A. The customer said B.
With Zometric
Element, sub-element, process-step and overall results are computed with the downgrading rules and the two-thirds rule. A star question scored 4 caps the class at B, whatever the score.
VDA 6.3 scoring
04Responses
Findings sit in the report and nobody answers them.
With Zometric
Issuing the report sets each nonconformity's due dates from the closing meeting and gives the response owner a follow-up action. Overdue responses are flagged on the finding and in the programme.
Finding due dates
05Effectiveness
We close a finding as soon as the answer arrives.
With Zometric
Completion and effectiveness are two separate decisions, and the response owner cannot verify their own finding. A finding with a CAPA closes only after the CAPA is closed.
Two verification decisions
06Layered audits
The LPA sheets are filled in, but the same “No” keeps coming back.
With Zometric
A “No” needs a comment and the action taken. When the same question gets another “No” in the area within 30 days, a CAPA is opened or the open one is linked.
LPA repeat rule
How it works
How an audit runs in Zometric
Each step has its checks: 48 audit rules flag what is missing, and open errors block the step they guard.
01
Universe · Risk
Build the universe and confirm intervals
List the processes, products, suppliers and functions to audit, with the shifts of each manufacturing process. The risk score proposes an interval of 3, 6, 12 or 36 months; a person confirms it with a reason of at least 20 characters.
02
Programme · Approval
Plan the year and have it approved
Propose the plan, and Zometric adds an audit for every item that is due or missing in the cycle, with the missing shifts and the handover. The audit client approves it, and the approved programme is kept as a numbered revision.
03
Preparation
Prepare the audit
Set objectives, scope, method and catalogue, and choose the VDA 6.3 elements. The lead auditor's eligibility is checked, and a manufacturing process audit records the released PFMEA and Control Plan revisions in force.
04
Fieldwork
Answer, collect evidence, record findings
The opening meeting starts the audit. Every finding needs a criterion, evidence and, for a nonconformity, a grading rationale; three questions propose major or minor. An immediate risk notifies the auditee representative and the audit client at once.
05
Report
Issue the report
The closing meeting sets the report due date, 14 days later by default. Issuing the report stores the VDA 6.3 results, opens the nonconformities with their due dates, closes observations and good practices, and freezes the report as a numbered revision.
06
Response · CAPA
Respond or open a CAPA
The response owner answers with containment, root cause, an action plan and similar processes checked, plus a correction for a minor. A nonconformity can open its CAPA instead, and the finding then follows the CAPA's progress.
07
Verification
Verify completion, then effectiveness
Someone other than the response owner verifies completion, which schedules the effectiveness check 90 days later by default. If the action was not effective, the finding returns to work, and a minor nonconformity against the corrective-action process is drafted or put to the programme manager.
08
Layered audits
Run layered process audits
Supervisors, area managers and plant management get their slots in a rolling schedule. They answer a short check sheet on a phone, and every “No” is followed up, notified and, if it repeats, escalated to a CAPA.
Want to see Audit Management on your own process?
A 30-minute call covers your products, your customers' requirements and the tools you use today.
What it does
Audit Management — what you actually get.
Each capability is tied to a decision your team is already trying to make.
Audit Universe & Risk-Based Programme
List everything that can be audited — processes, areas, suppliers, shifts — and let risk set the frequency: open findings, the last audit result, complaints. The programme shows coverage at a glance, including the shifts nobody has audited yet.
System, Process & Product Audits
One lifecycle from planning through fieldwork, report and follow-up to closure. Scope, audit team, checklist, evidence and report on one record, with the report issued as a frozen, numbered version.
VDA 6.3 Scoring
Answer the questions and the result is computed for you — element scores, overall compliance, the downgrading rules and the final A / B / C classification, including the potential analysis. Load your licensed questionnaire once and use it on every audit.
Findings That End in a CAPA
A grading assistant proposes the severity, due dates are set when the report is issued, and a finding can open its CAPA directly. Implementation and effectiveness are verified as separate decisions — and the finding closes only when its CAPA does.
Auditor Qualification & Eligibility
Auditor qualifications and evaluations on record, with team eligibility checked as you assign people — so the audit a customer later questions was demonstrably run by a qualified, independent auditor.
Layered Process Audits on the Phone
Layers, areas, schedules and a question bank that can be generated from the Control Plan. Auditors answer on a phone — offline if the signal drops — and every "No" records what was seen and the action taken, with a photo if needed. A repeated "No" escalates to a CAPA.
Supplier Audits & Management Review
Second-party audits of suppliers, who answer their findings through the Supplier Portal. Completion rates, the Pareto of LPA "No" answers and programme effectiveness are ready for the management review without a week of slide-building.
In numbers
How a VDA 6.3 result is classified
Each question scores 0, 4, 6, 8 or 10. An element's result is its points as a share of the points possible, the overall result pools every audited question, and the class follows: A from 90 %, B from 80 %, otherwise C. Downgrading rules then cap the class, so a high score alone does not guarantee an A.
90
% overall, EG(P5P6P7)
A
Class by score
B
Final class after downgrading
Process audit of elements P5–P7, one process step — sample answers
Element
Questions
Points
Possible
Result %
Check
P5 Supplier management
Questions7
Points66
Possible70
Result %94
CheckNo rule triggered
P6 Production process analysis
Questions26
Points228
Possible260
Result %88
CheckStar question P6.2.3 scored 4
P7 Customer care, satisfaction and service
Questions5
Points48
Possible50
Result %96
CheckNo rule triggered
EG(P5P6P7) overall
Questions38
Points342
Possible380
Result %90
CheckA by score, capped at B
P6 reached 88 % and none of its six sub-elements fell below 80 %, but star question P6.2.3 scored 4, so rule DG-B3 caps the class at B. An element below 70 % or a star question scored 0 would cap it at C, and a class C result plans a repeat audit within 90 days by default.
Connected modules
How Audit Management connects to the rest of Zometric
Audits read risk from the engineering documents and hand their problems to CAPA, so nothing is retyped between modules.
Maintains the universe, the programme and the auditor records, issues reports and manages findings. Quality managers have the same rights.
Audit client
Approves the audit programme or sends it back with a comment. Only the audit client named on the programme can approve it.
Lead auditor and audit team
Prepare and conduct the audit, record answers, evidence and findings, and verify responses — never a finding they own themselves.
Auditee and response owner
See their audit, acknowledge or dispute findings, and submit the response for the findings they own.
LPA process owner and area owners
Run the layered audit programme and its follow-up actions. Area owners manage their own area, and overdue follow-ups escalate to the process owner.
Layered auditors
Perform the LPAs scheduled for them, including slots they take over as a substitute. Supplemental, visitor and practice LPAs are open to others when the programme allows them.
Comparison
Zometric Audit Management vs paper checklists and a spreadsheet
Zometric Audit Management vs paper checklists and a spreadsheet
Zometric Audit Management vs paper checklists and a spreadsheet
Paper checklists and a spreadsheet
Zometric Audit Management
Audit frequency
Paper checklists and a spreadsheetSet by habit, rarely revisited
Zometric Audit ManagementProposed from a risk score, confirmed with a reason, reopened by complaints and changes
Shift coverage
Paper checklists and a spreadsheetNot tracked per shift
Zometric Audit ManagementEvery shift and the handover shown as covered, planned or missing in the three-year cycle
VDA 6.3 class
Paper checklists and a spreadsheetFormulas in a workbook, downgrading applied by hand
Zometric Audit ManagementComputed with the downgrading rules, the two-thirds rule and P1 classification
Auditor eligibility
Paper checklists and a spreadsheetA separate qualification matrix
Zometric Audit ManagementChecked when a person is assigned: qualification, experience, VDA 6.3 exam, independence
Finding deadlines
Paper checklists and a spreadsheetTyped into the report
Zometric Audit ManagementSet from the closing meeting when the report is issued, with overdue flags
Closure
Paper checklists and a spreadsheetClosed when the answer arrives
Zometric Audit ManagementCompletion and effectiveness verified separately; a finding with a CAPA waits for the CAPA
Layered audits
Paper checklists and a spreadsheetPaper sheets typed up at the end of the week
Zometric Audit ManagementAnswered on a phone, offline if needed; a repeated “No” escalates to a CAPA
Checks
Paper checklists and a spreadsheetNone
Zometric Audit Management48 audit rules and 20 LPA rules; errors block the step they guard
Want to see Audit Management on your own process?
A 30-minute call covers your products, your customers' requirements and the tools you use today.
Standards & Compliance
Built for the standards your regulators and customers already require.
IATF 16949
VDA 6.3
ISO 9001
ISO 19011
AIAG CQI-8 (LPA)
Integrations
Data in and out
Audit programme workbook
Export the programme to Excel: the month-by-month plan per universe item, cycle coverage with shift gaps, programme effectiveness, and risks and opportunities.
Audit report and VDA 6.3 results
The issued report with a print layout, and Excel workbooks of the report and findings and of the VDA 6.3 result matrix, including the P6 question-by-step matrix and the P1 summary.
Question catalogue texts
Paste your licensed question texts and minimum requirements from Excel into the seeded VDA 6.3 structure. Codes that do not match are reported, never created.
LPA KPIs and check sheets
Export LPA results to Excel — completion by layer, conformance by area, a Pareto of “No” answers and every “No” with its action — and the weekly check sheet of an area.
REST API
Audits, their status transitions, answers, findings and results, and layered audits — start, answer, complete and KPIs — are available through the REST API.
FAQ
Audit Management: frequently asked questions
Straight answers to the questions teams ask before a demo.
What does audit management software do for IATF 16949?
It keeps the internal audit programme risk-based and complete. Zometric lists every process, product, supplier and function to audit, proposes each interval from a risk score, shows which shifts and shift handovers are covered in the three-year cycle, and follows every nonconformity from the report to verified effectiveness, so the programme can be shown to a certification auditor as one record.
How does Zometric set how often an area is audited?
Each universe item gets a risk score from open findings, its last audit result, customer complaints, High Action Priority PFMEA chains, recent changes and an ineffective CAPA. By default, 0–2 points is low risk (36 months), 3–6 medium (12), 7–11 high (6) and 12 or more very high (3 months). A low-risk item that is not fully compliant gets the medium interval, and a person confirms every interval with a written reason.
How is a VDA 6.3 process audit scored in Zometric?
Each question scores 0, 4, 6, 8 or 10 points. Zometric computes the element, P6 sub-element, process-step and overall percentages, classifies A from 90 %, B from 80 % and C below, then applies the downgrading rules: an element or step below 70 % or a star question scored 0 caps the class at C; an element between 70 % and 80 %, a sub-element below 80 %, a star question scored 4 or any question scored 0 caps it at B.
Does Zometric include the VDA 6.3 question texts?
No. Zometric ships the VDA 6.3 (2023) structure — elements P2 to P7, 59 questions, 18 star questions and the P1 potential-analysis set — with short labels only. You load your licensed question texts and minimum requirements once by pasting them from Excel, and every audit then uses them.
When are responses to audit findings due?
Due dates count from the closing meeting and are set when the report is issued. By default, a major nonconformity needs its first response in 15 days, the full response in 60 days and verification in 90 days; a minor nonconformity needs its response in 60 days. A customer's own response times or the audit type can replace these defaults.
When is an audit finding closed?
A nonconformity closes only after two separate decisions by someone other than its response owner: completion verified, then effectiveness verified, by default 90 days later. If the finding opened a CAPA, effectiveness can be confirmed only after the CAPA is closed. Observations and good practices close when the report is issued.
How do layered process audits work in Zometric?
Layers such as supervisors, area managers and plant management are scheduled across areas and shifts. Auditors answer Yes, No or N/A on a phone, and answers are kept on the device if the connection drops. A “No” needs a comment and the action taken; a repeated “No” on the same question in the area within 30 days escalates to a CAPA by default.
Can suppliers answer audit findings in Zometric?
Yes. For a second-party audit, a supplier answers each nonconformity through the Supplier Portal with containment, root cause, a corrective action plan and the similar processes checked. The answer arrives as a submitted response, and the auditor accepts or rejects it with a reason before the finding moves on.
See Audit Management running on your line.
A 30-minute discovery call. A 2–3 week pilot on real factory data. Then scale at your pace.